Orders Displayed2
Scheduled Step Qty0
Finished Units Not Fully Planned86
Orders At Risk2
CH 60 ROLLOVER / Production Order 14
Plan window: 2026-10-25 through 2026-09-11
AT RISK
Order Quantity50
Finished0
Scheduled Step Qty0
Finished Units Not Fully Planned50
Next Planned DateNone
Calculated CompletionNot fully scheduled
Completion Due2026-09-11
Limiting MaterialCH 60'' SEAT short 50 ea
50 finished units cannot currently be scheduled by the due date.
No dated production steps are currently planned for this order.
Bar Chair Regular Size back - 1600 / Production Order 13
Plan window: 2026-10-25 through 2026-09-14
AT RISK
Order Quantity36
Finished0
Scheduled Step Qty0
Finished Units Not Fully Planned36
Next Planned DateNone
Calculated CompletionNot fully scheduled
Completion Due2026-09-14
Limiting MaterialFabric Yadkin Oatmeal short 18 yd
36 finished units cannot currently be scheduled by the due date.
No dated production steps are currently planned for this order.