ProdLine V1
Production Completion

Finished quantities are counted when they complete the final build step. Today includes completed runs through the current time.

Finished Today 2
Work Orders Satisfied Today 0
Open Work Orders 4

Work Order Status

A work order is satisfied when finished quantity at its final operation reaches the ordered quantity.

Work OrderProductDueOrderedTodayFinishedRemainingStatusSatisfied At
9Table2026-09-075005 NOT STARTED Not yet
8Sofa2026-09-075005 NOT STARTED Not yet
7Chair2026-09-075005 NOT STARTED Not yet
10EndTablexyz2026-09-084222 IN PROGRESS Not yet

Completed Items by Day

Daily totals include only non-cancelled runs that ended at the final operation during the selected dates.

DayWork OrderProductFinished QtyFirst CompletionLast Completion
2026-09-0110EndTablexyz209:3109:47