Product Production Setup
Build the product route from top to bottom. Add the work steps first, then assign materials and SOP/shop-paper filenames to each step.
Product: CH 60 ROLLOVER (Build #10)
3
Add Materials to the Selected Step
Enter how much material is consumed when one item completes this step.
No step selected. Select a step in section 2 before adding materials.
| No materials have been added to the selected step. |
4
Add SOP Files to the Selected Step
List the Dropbox filenames employees need at this station. A step may have any number of files and file types.
Files for the Selected Step
First choose a step in Section 2, then identify the Dropbox file used at that station.
No step selected. Select a step in section 2 before adding SOP files.
Files Assigned to the Selected Step
| No SOP/shop-paper filenames have been added to the selected step. |
5
Product Setup Quick View
Review the complete route, time, materials, and SOP files for this product.
5 steps34 minutes per item7 material entries0 SOP files
Review setup: 1 step(s) have no materials listed. This may be intentional.
Step 1 — FABRIC CUTTING5 minutes per item
• MADRID BLACK — 4 yd per item
No SOP files listed.
Step 2 — SEWING15 minutes per item
• T-90 AMANN — 50 yd per item
No SOP files listed.
Step 3 — FOAM PREP2 minutes per item
• Foam Pack — 1 set per item
No SOP files listed.
Step 4 — UPHOLSTRY5 minutes per item
• CH 60'' BACK — 1 ea per item
• CH 60'' SEAT — 1 ea per item
• Foam Pack — 1 set per item
• MADRID BLACK — 1 yd per item
No SOP files listed.
Step 5 — PACKING7 minutes per item
No materials listed (may be intentional).
No SOP files listed.